SO CLOSE! ... 98% COMPLETE!
Primary LARTC construction is now 98% complete! Following
are the construction phases and timetable, represented
visually to the right, beginning at the bottom with 0 and
ending with E at the top that represents exterior work to be
completed during the second half of construction.
__________________________
E. Exterior Work (2019-21)
4. Training Addition (2019-21)
3. Atrium - Lobby, Auditorium, Mezzanine (2019-20)
2. Housing, Kitchen (2017-19)
1. Training, Administration, Production (2016-17)
0. Road/ Culvert/ Site Prep/ Utilities (2014-15)
__________________________
The chart to the right shows the percentage completed for
each phase, square feet of building for phases 1-4 and the
budget for each phase.
We are humbled to think that so many churches, individuals
and ministries have now invested $1.92 million in the LARTC
project! Looking back strengthens our faith to look forward.