Construction Timetable and Milestones

Next... Construction Work Remaining
 
LARTC Timetable and MilestonesLARTC Timetable and Milestones

Following are some important milestones. Celebrate with us!

Nov. 2012 - Panama A/G Presbytery unanimously designates Rana de Oro property for the LARTC.

Fall 2015 - Creek is bridged, road extended, land cleared and leveled.

Feb. 2016 - Lincolnton, GA MAPS team launches construction.

Feb. 20, 2017 - Move-in day!

March 9, 2017 - Dedication of Phase 1 Training/Admin Building.

Next... Construction Work Remaining

Aug. 2017 - First month-long Advanced training seminar.

Winter 2018 - Atrium roofed; Bakersfield begins construction.

Oct. 2018 - Miracle offering to complete the 2nd floor Housing building!

Feb. 2019 - 13 additional guestrooms completed.

March 2019 - International Dialogue occupies all 23 guestrooms!

April 2019 - Atrium roof installed; Training addition started.

July 2019 - Atrium mezzanine/stairs completed, windows/doors installed; Commerical kitchen equipped.

Oct. 2019 - Training addition floors poured and exterior walls completed; Atrium construction completed.

Dec. 2019 - Atrium completed (except for A/C installation)!

Feb. 2020 - Atrium A/C installation begun.

Nov. 2020 to Jan. 2021 - Perimeter security wall and gate completed.

Feb. 2021 - Road and parking lot base laid and surfaced, parking lot lights.

Mar. to May 2021 - Roof facade/soffit built on front of building.