Fall 2016 Construction Photos
Phase 1 building exterior block
work is complete. Two-story stairwell constructed.
Exterior stucco work about 40% completed, on schedule to
finish by the end of November.
Second floor interior wall work and
bondbeams are virtually finished, with final work being done
on the two hallway bathrooms. Interior stucco work is
finished on the first floor and 50% complete on the second
floor.
Six power poles with street lights have
been installed from the street to the building. Main cable
has been run to the transformer well. The 150 KW transformer
has been installed and wired to the main switch.
Building wiring has begun.